Time and Work - Complete Guide | Quantitative Aptitude

Select PDF Type

๐Ÿ“Š
Formula Sheet
๐Ÿ“
PYQs (Previous Year Questions)
๐Ÿ“‹
Syllabus

Time and Work: Complete Guide with Formulas, Theory, and Examples

Time and Work is one of the most important and scoring topics in quantitative aptitude, frequently appearing in competitive exams like SSC, Banking, Railways, and others. Mastering this topic requires a strong understanding of basic concepts, formulas, and problem-solving strategies.

View in Hindi Start Practice Download PDF

1. Basic Concepts

Work

Work refers to any task that requires effort to complete. The total work is usually considered as 1 unit or 100%, which can be divided among people working together.

Time

Time is the duration required to complete a work. If a person can complete a task alone in a certain number of days, their efficiency can be calculated.

Efficiency

Efficiency is the rate at which a person can complete work.

Efficiency = Work Done / Time Taken

Observation

  • More efficiency → Less time to complete work
  • Less efficiency → More time to complete work

Relation Between Work, Time, and Efficiency

Work Done = Efficiency × Time

2. Fundamental Formulas

Work Formula

W = R × T

Where:
W = Total work
R = Rate of work or efficiency
T = Time taken

Individual Work

If A can do a work in x days and B can do the same in y days:

  • Work done by A in 1 day: 1/x
  • Work done by B in 1 day: 1/y

Combined Work

Days required together = (x × y) / (x + y)

Work with Different Hours

If efficiencies differ or multiple people work different hours:

Work done in a day = Sum of individual efficiencies × hours worked per day

Work Fraction Method

Total work = 1 unit (or 100%)
Fraction of work done = Time spent / Total time required

3. Types of Problems in Time and Work

Single Person Work

Basic calculation: If a person completes work in x days, the work done in 1 day = 1/x.

Multiple Persons Working Together

Use efficiency method: Sum the 1-day work of all persons.

T = 1 / (A's 1-day work + B's 1-day work)

Persons Working Alternately

  • Calculate work done in 1 cycle (A + B)
  • Repeat cycles until the remaining work is left
  • Solve remaining work separately

Persons Joining or Leaving Midway

  • Calculate the work done by each group separately
  • Total work = Sum of work done in each phase

Efficiency Ratio Problems

If efficiency ratio of A : B : C = 2 : 3 : 5, then divide total work in same ratio.

Time taken by each person = Work assigned / Efficiency

Pipe and Cistern Problems (Time and Work Applied)

Water filled or emptied = Work
Rate of filling/emptying = Efficiency

Total Time = Total Capacity / Net Rate of Flow

Work with Different Hours per Day

  • Calculate total units of work done per day for each person
  • Add them for combined daily work
  • Total time = Total work ÷ Daily combined work

4. Advanced Concepts

Work and Wages Problems

Wages are proportional to the work done.

Individual Wage = (Individual Work / Total Work) × Total Wages

Work with Efficiency Changes

If efficiency increases or decreases after some days:

Total Work = (Old Efficiency × Old Days) + (New Efficiency × New Days)

Work with Fractional or Partial Completion

If a person does a fraction of work alone, calculate remaining work and divide by combined efficiency to find time required.

5. Key Tips and Tricks

Important Tips:
  • Always assume total work = 1 unit for simplicity
  • Use efficiency per day to avoid confusion in multiple-person scenarios
  • Alternate work problems can often be solved by finding work per 2-day or multi-day cycles
  • Pipes, cisterns, and machines follow same time and work principles
  • For ratio efficiency problems, always convert ratio to actual efficiency using a common multiplier
  • Break complex problems into phases, calculate work for each phase, then sum

6. Examples

Basic Problem

Example 1:

A can complete a work in 10 days. How much work will A do in 4 days?

Solution:
Work done per day = 1/10
Work in 4 days = 4 × (1/10) = 2/5 of total work

Multiple Persons

Example 2:

A can do a work in 6 days, B in 8 days. Find days required together.

Solution:
1-day work: A = 1/6, B = 1/8
Combined 1-day work = 1/6 + 1/8 = 7/24
Total time = 24/7 ≈ 3.43 days

Efficiency Ratio

Example 3:

A : B : C = 2 : 3 : 5, Total work = 100 units

Solution:
Efficiency per day: assume multiplier = 1
A = 2 units/day, B = 3 units/day, C = 5 units/day

Pipe Problem

Example 4:

Tank can be filled by Pipe A in 12 hours and emptied by Pipe B in 20 hours. Time to fill tank with both pipes open:

Solution:
Net work/day = 1/12 - 1/20 = 5/60 - 3/60 = 2/60 = 1/30
Time = 30 hours

7. Summary of Formulas

Concept Formula
Work Done Work = Efficiency × Time
1-day work 1-day work = 1 / Total days
Combined Work 1-day work together = Sum of individual 1-day work
Days Required Together T = xy / (x + y)
Wages Distribution Individual Wage = (Individual Work / Total Work) × Total Wages
Pipe/Cistern Time = Total Capacity / Net Rate

Conclusion

Time and Work is a highly logical topic in aptitude. By understanding basic concepts, memorizing key formulas, and practicing different types of problems—like multiple persons, alternate work, efficiency ratios, and pipe problems—you can solve almost all questions quickly. Efficiency methods and unit work methods are particularly powerful in competitive exams.

Featured Courses
Master Quantitative Aptitude with Our Specialized Resources
Choose from our expertly crafted Resources designed to help you excel in quantitative aptitude.

Arithmetic

Mastering numbers through basic operations
POPULAR
2500+ Practice Questions
500 Comprehensive Tests
Bilingual Support
Step-by-step solutions

Algebra

Master the fundamentals of Algebra
FREE
1500+ Practice Questions
300 Comprehensive Tests
Bilingual Support
Real exam questions

Geometry

Complete guide to Mathematical Figures
NEW
2000+ Practice Questions
400 Comprehensive Tests
Bilingual Support
Shortcut techniques